Sails Pavilion

Rebuild Rooftop Chillers

Sails Pavilion Rooftop Chillers
May 2016

Sails Pavilion before construction. As part of its $25.5 million infrastructure state loan, the facility’s rooftop chillers that power our HVAC system will be replaced.
Project Overview

Complete replacement of two chillers that service the Sails Pavilion. 

Timeline: 
December 6, 2016 to February 28, 2017
Type: 
I-Bank Financed Loan
Location: 
Sails Pavilion
Cost: 
$619,274
Status: 
100% Complete