Lower Level, Mezzanine, and Upper Level

Escalator Modernization

Escalator Modernization
May 2017

Installed in 1989 when the facility opened, the escalators are being modernized in the West Building as part of the I-Bank Funded Projects approved by the Board of Directors. This image shows the escalators in Lobby C are upgraded.
Project Overview

Eight escalators located in the West Building will be modernized. Escalators will be taken out two at a time: one in the front lobby and one in the back of the venue. Each project averages about 12 to 13 weeks per escalator upgrade.

Timeline: 
April 1, 2017 to December 25, 2018
Type: 
I-Bank Financed Loan
Location: 
Lower Level, Mezzanine, and Upper Level
Cost: 
$3,597,885
Status: 
45% Complete