Escalator Modernization

Escalator ModernizationMay 2017Installed in 1989 when the facility opened, the escalators are being modernized in the West Building as part of the I-Bank Funded Projects approved by the Board of Directors. This image shows the escalators in Lobby C are upgraded.
Project Overview

Eight escalators located in the West Building will be modernized. Escalators will be taken out two at a time: one in the front lobby and one in the back of the venue. Each project averages about 12 to 13 weeks per escalator upgrade.

Timeline: 
April 1, 2017 to December 25, 2018
Type: 
I-Bank Financed Loan
Location: 
Lower Level, Mezzanine, and Upper Level
Cost: 
$3,597,885
Status: 
100% Complete